|
| Economics and Financing |
| Economics |
|
| Most
inlet cooling projects are conceived as back-fits to existing plants
for three reasons:
1. Most gas turbine OEMs are not in the business of providing inlet cooling systems, so they have no incentive to promote the technology.
2. Most developers
and bankers don't have experience with the technology. Being rather
conservative to new technology risk, they tend to put off the decision
for a later date, after startup, taking a wait-and-see attitude.
3. Most older
Power Purchase Agreements did not recognize a financial incentive
to provide additional power during periods of tight summer reserve
margins.
|
|
| So
once a plant is up and running, most operators quickly become disappointed
with their gas turbine's summer output. Only then do they start looking
seriously at inlet cooling technology. Unfortunately, it is sometimes
too late to add cooling for several technical reasons: |
- Not enough room for refrigeration equipment
- No space left for cooling coils in the inlet filter house
- Transformer cooling would be undersized
- Cooling tower and condenser undersized (for combined cycle plants)
|
|
| However, there
is more often a financial reason for not adding inlet cooling: |
- Uncertainty in predicting future performance
- Too long a payback period
- Restrictive covenants in original finance agreements
- Power Purchase Agreement (PPA) doesn't allow major upgrades
|
|
| While Polar Works can't fix all of the above problems, you'd be surprise just how many we can effectively handle. |
|
| In
general, we see that a properly designed inlet cooling system can
have as much positive financial impact as building a new peaking station
just for the summer load. The manageability of the augmented power
capabilities will be improved as compared to a new peaker. The inlet
cooling system can be built and financed with much less regulatory
and schedule risk than adding new capacity. Further, the cost of adding
inlet cooling to an existing site will be much less than adding a
new plant that can make up for that lost summer output. Our outlook
is that if adding inlet cooling is much less than the cost of building
a new plant, then the cooling project should be undertaken. Unfortunately,
so many projects never get past the feasibility study stage, because
of some constraints that occur at the project finance level. Here's
the explanation... |
|
 |